California's New Change-Order Payment Law for Contractors (SB 440)
By Yan Payments
What does California’s new change-order law require?
Starting with private construction contracts signed on or after January 1, 2026, California’s SB 440, the Private Works Change Order Fair Payment Act, requires the owner to respond in writing to a contractor’s change-order claim within 30 days, approving it, rejecting it, or splitting it into disputed and undisputed amounts. Undisputed amounts have to be paid within 60 days. Miss that, and the unpaid amount accrues interest at 2% a month, which works out to 24% a year.
If you’re a general contractor, subcontractor, or construction-adjacent service business in California, this changes how change orders get resolved on jobs you’re signing now.
Who does this apply to?
Private works contracts, meaning private (non-public) construction projects, entered into on or after January 1, 2026. It’s codified at Civil Code Section 8850 and runs through January 1, 2030 under current law. The requirements can’t be waived by contract, so a clause in your agreement that tries to override the 30- and 60-day clocks doesn’t hold up.
Contracts signed before January 1, 2026 aren’t covered, even if change orders on that job get submitted later. And if you’re doing ongoing work under a master agreement or series of task orders, check the date each task order or amendment was actually signed, since a change order issued under a new task order after January 1, 2026 can fall under the law even if the master agreement predates it.
How is this different from the old process?
Before SB 440, there was no statewide deadline forcing an owner to respond to a change-order claim at all. A contractor could do the extra work, submit a change order, and then wait weeks or months for an answer, all while carrying the cost of labor and materials. SB 440 builds on California’s existing Prompt Payment Act and adds a specific, nonwaivable timeline just for change orders:
- Owner responds in writing to the claim: 30 days
- Owner pays the undisputed portion: 60 days (from the written response)
- Interest on late undisputed payment: 2% per month (24% annualized)
- Disputed portion, if any: goes to non-binding mediation, costs split evenly, before arbitration or litigation
The 30-day window can be extended, but only if both sides agree to it in writing for that specific claim.
What happens if the owner doesn’t pay?
Contractors and subcontractors who follow the law’s required notice steps get a right to stop work on the project without being penalized for it, even if their contract has a no-suspension clause. Private contracts frequently try to bar a contractor from walking off a job over a payment dispute, and SB 440 overrides those provisions once its conditions are met. Different legal summaries describe the exact notice sequence a bit differently, so if you’re considering invoking this right, get the specific steps confirmed by a construction attorney before you act. This article is general information, not legal advice.
What should a contractor actually do differently now?
A few habits make this law work for you instead of against you:
- Submit change orders in writing, with a clear scope and price, so the 30-day clock has something concrete to measure against.
- Track the date you submit each claim. If 30 days pass with no written response, that’s worth a follow-up letter referencing Civil Code Section 8850, not just a phone call.
- Separate disputed and undisputed amounts yourself when you submit, so there’s less room for an owner to leave the whole claim “pending” instead of paying the part they don’t actually contest.
- If you invoice through ACH or check rather than card, make sure your invoicing system can flag aging change-order claims the same way it flags overdue invoices, since the 60-day payment clock is now a real deadline with interest attached.
This law doesn’t fix slow-paying owners by itself, but it gives contractors a dated paper trail and a real cost (2% a month) for owners who sit on undisputed amounts.
Sources