California's New 5% Retention Cap on Construction Payments (SB 61)

By Yan Payments

How much can a GC or owner hold back now?

No more than 5% of any progress payment, and no more than 5% of the total contract price overall. That’s the new rule under California’s SB 61, which added Civil Code Section 8811 and took effect January 1, 2026. Before this, 10% retention was standard on private jobs, and some contracts held back even more. The cap applies at every tier: owners withholding from direct contractors, and direct contractors withholding from subs, all capped at the same 5%.

Does this apply to your contract?

Only if it was entered into on or after January 1, 2026. SB 61 isn’t retroactive, so if you signed before that date, the old 10% retention term in your contract still stands for that agreement. There’s a wrinkle worth knowing about if you work under a master agreement or ongoing contract: a new task order, change order, or follow-on agreement executed after January 1, 2026 can fall under the new cap even if the original master agreement predates it. If you’re not sure which bucket a given job lands in, check the date the specific task order or purchase order was signed, not just the date of the umbrella contract.

Who’s exempt from the 5% cap?

Two carve-outs matter most. First, if a subcontractor is told it needs to provide a performance and payment bond and doesn’t furnish one, the cap doesn’t protect that sub. Second, the law excludes residential projects that aren’t mixed-use and don’t exceed four stories. Neither “residential” nor “mixed-use” is spelled out in the statute itself, so a mixed-use mid-rise or a borderline project type is worth running past a construction attorney rather than assuming either way.

What’s the penalty if an owner or GC ignores the cap?

The statute includes a mandatory attorneys’ fees award for the side that successfully enforces compliance. That changes the math for a contractor weighing whether to push back on an over-retention clause: it’s no longer a case of spending legal fees to recover a percentage point of retention. If you win, the other side pays your fees. There’s also a non-waiver provision tied to Section 8820, meaning a contractor generally can’t sign away this protection just because a contract says so.

What should subcontractors actually do differently now?

A few concrete steps:

  • Pull every active and pending private-project contract and check the signature date against January 1, 2026.
  • If a new contract or task order comes across your desk with a retention clause above 5%, flag it before signing. It may simply be outdated boilerplate the other side hasn’t updated.
  • If you’re a sub and the general contractor is told a bond is required, get that bond in place. Skipping it is the one thing that can knock you out of the cap’s protection.
  • Factor the lower retention into your cash flow planning. Going from 10% held back to 5% on a $500,000 contract is $25,000 that stays in your account instead of sitting with the owner until closeout.
  • Know about SB 440 too. It’s a companion law, also effective January 1, 2026, that sets new rules for how change-order and time-extension disputes get resolved on private works. If retention disputes on your jobs usually start as change-order fights, that’s the law governing the process now.

Does this fix the cash-flow problem for good?

It helps, but it doesn’t eliminate the wait. Retention still isn’t released until project closeout, sometimes months after your last day on site, and 5% of a six-figure contract is still real money. Getting paid faster on the progress payments you are owed, rather than the portion held back, is the piece a contractor can control directly. If you’re still invoicing with paper checks or waiting on mailed payments from GCs, that lag compounds the retention delay instead of offsetting it. We built our invoicing tool so contractors can send an invoice with a payment link attached and get paid by ACH or card without waiting on a mailed check.

This is general information about California law, not legal advice. If you’re negotiating a specific contract or disputing a retention clause, talk to a construction attorney about your situation.

Sources:

  • Foley and Lardner, “No More 10% Retainage: California Mandates 5% Retention Cap on Private Construction Projects”
  • Akerman, “New 5% Retention Cap for California Private Projects: Key Impacts for Contracting Parties”
  • Allen Matkins, “California’s New 5% Retention Law: What Changes in 2026”
  • Gravel2Gavel (Pillsbury), “New California Law Imposes a Five Percent Cap on Retention for Private Works of Improvement”

← Back to all posts